Technology company Wärtsilä will supply a 282 MW onsite power solution for a data center to be built in the U.S. The order was placed by a major U.S. independent power producer. The plant will be equipped with 15 Wärtsilä 50SG gas engines. The order demonstrates the need for fast-starting, onsite power generation. This is due to the power supply challenges of new data center projects due to power transmission bottlenecks, grid connection delays, and increased demand for AI-driven electricity. The order was booked in Wärtsilä’s order book for the third quarter of 2026.
The project will further consolidate Wärtsilä’s position in the fast-growing data center power generation market in the U.S. This is Wärtsilä’s seventh data center order in the U.S. With the order, the company’s total power generation capacity in the U.S. for data center needs will increase to over 3 gigawatts. The customer chose Wärtsilä’s engine-based solution because it can provide large-scale power generation capacity on a fast schedule and gradually increase capacity as computing power demand increases.
The Wärtsilä 50SG engines operate very efficiently in harsh conditions. Their closed-loop cooling system consumes very little water compared to traditional condensing power plants, and the engines can be converted to run on future fuels. The main benefits for developers of data center projects are reliable power supply, scalable generation capacity, and the possibility of alternative solutions in the future.
“Traditional energy infrastructure is not keeping pace with the growth of the U.S. data center market,” said Risto Paldanius, Vice President, Americas, Wärtsilä Energy. “This order is a good example of how flexible on-site power generation can help developers ensure reliable power supply, reduce deployment risks, and increase operational efficiencies. The growth of our data center deliveries to date shows how flexible motor technology can be a key solution to one of the most significant challenges in the growth of the data center industry.”
Wärtsilä’s equipment will be delivered in 2028, and the plant is scheduled to be fully operational in 2029.